Back to Glossary
Project Management
Earned Value Management
Quick Definition
An integrated project management methodology that combines scope, schedule, and cost data to assess project performance and progress.
Detailed Explanation
EVM uses three key measurements: Planned Value (PV — what was planned to spend), Earned Value (EV — the value of work actually completed), and Actual Cost (AC — what was actually spent). From these, performance indices and forecasts are calculated.
Key formulas include: SPI = EV/PV (schedule performance), CPI = EV/AC (cost performance), EAC = BAC/CPI (estimate at completion), and ETC = EAC − AC (estimate to complete). SPI and CPI values below 1.0 indicate underperformance.
EVM is heavily tested in the PMP® exam and is one of the most powerful tools for early detection of cost and schedule variances.
Related Terms
Relevant Frameworks
PMBOK